Queens Long Island City-Hunters Point
DOB violations
Department of Buildings violations attached to this BIN or tax lot.
49 records
| Date | Status | Type | Summary |
|---|---|---|---|
| Sep 14, 2023 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | EMERGENCY WORK ORDER.EXP4 WALL@MEZZ WAS PRTLLY DTACHD W/VERTCRCK FROM FROM MAIN ROOF TO TOP OF MEZZ ROOF.EXP4 WALL INADEQUATELY UNBRACD &IN DANGER OF COLLAPSE.CRCK MONITORNG RPORTS INDICATD MOVEMENT OF WALL OWNR TO RTAIN NYS PE&GC TO IMMED1.BRACE&SHORE EXP4CRCKD MEZZ WALL,AS REQ'D,2.INSTALL TEMP SHORNG BELOW UNSUPPORTD STEEL |
| Aug 11, 2023 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | ADDITIONAL INFORMATION.APPRX 113FT AT EXP1 ALONG 25FT,BY 300FT@EXP2 ALONG 51 AVE.EXP4 ADJ TO OPEN LOT IN USE BY NYPD BELOW LIE EXP4 WALL INADEQUATELY BRACED&POSED DANGR TO ADJ NYPD LOT BELOW.IMMEDIATELY COMPLY WITH COMMISSIONER'S ORDER #343068 |
| Aug 3, 2023 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | EMERGENCY WORK ORDER.EXP4WALL@MEZZANINE LVL HAD VERT CRCKWHERE BULKHEAD WALL&EXP4 WALL PRTLLY DTACHD.EXP4WALL WAS INADEQUATELY BRACED &POSED A DANGER TO THE ADJ NYPD LOT BELOW.IMMED COMPLYW/COMMISSIONER'S ORDER#343056(071023FEU40201PN)DATED JULY 10,2023 TO IMMEDIATELY ERECT TIGHTBOARD FENCE |
| Aug 3, 2023 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | ADDITIONAL INFORMATION.APPRX 113FT AT EXP1 ALONG 25FT,BY300FT@EXP2 ALONG 51AVE.EXP4 ADJ TO OPEN LOT IN USE BY NYPD BELOW LIEEXP4 INADEQUATELY BRACED&POSED DANGR TO ADJ NYPE LOT BELOW.IMMEDIATELY COMPLY WITH COMMISSIONER'S ORDER #343068 DATED AUGUST 3,2023 |
| Jul 10, 2023 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | EMERGENCY WORK ORDER.EXP4WALL@ MEZZANINE LVL HAD VERT CRCKWHERE BULKHEAD.WALL&EXP4 WALL PRTLLY DTACHD.EXP4WALL WAS INADEQUATELY BRACD& POSED A DANGER TO THE ADJ NYPD LOT BELOW.OWNR TO RTAIN NYS PE&GC TO ERECT TGHTBRD FENCE IMMED@EXP4 ADJ NYPD LOT EXTNDNG20FT OUT FRM FACE OF EXP4WALL&30FT WIDE |
| Jun 26, 2023 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | FTM-EXP1&2 CRCKD&SPOILING.EXP1/2 CRNR W/VERT CRCKS&BULGING WALL.LINTEL @EXP2 SAGGING.WOOD GIRDER SAGGING&CRCKD.ROOF JOIST POORLY SUPPORTD BULKHEAD MSNRY WALL@EXP4 CRCKED.IMMEDIATELY.COMPLY WITH COMMISSIONER'S ORDER 357033(062323FEU40203PN)DATED 6/23/23 TO REPAIR BLDG UNDER PERMIT |
| Jun 23, 2021 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | EWO-WAREHOUSE-STUCCO@EXP1&2 CRCKD&SPALLING THROUGHOUT.STEEL HEADER ABVE ROLLUP GATE@EXP2 SEVRLY SAGGING W/MSNRY CRCKD&LOOSE.EXP1/2CRNR WALL CRCKD&BULGING OUT @EXP1.BLDG REPRSNTS A DANGER TO PUBLIC. OWNR TO RTAIN LIC. CONTRCTR-INSTLL SIDEWALK SHED ALONG EXP1&2 LENGTH.FILE W/IN 2DAYS FROM STRTOF WRK.STRT WRK BY 6/24/21&CONTINUE DAILY UNTIL COMPLTE |
| Jun 23, 2021 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | FTM-EXP1&2 CRCK&SPOILING.EXP1/2CRNER W/VERT CRCKS&BUILGING WALL.LINTEL @EXP2SAGGING.WOOD GIRDER SAGGING&CRACKED.ROOF JOIST POORLY SUPPORTED BULKHEAD MSNRY WALL@EXP4 CRCKD.OWNR RTAIN NYSPE-EVALU BLDG&PREPR&FILE DWGS W/DOB.RPAIRS STRT UNDR PRMT BY 08/13/2021 & COMPLTD BY 10/8/2021 |
| Jun 23, 2021 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | EWO-WAREHOUSE-EXP1&2 CRCKD&SPOILING.EXP1/2 CRNR W/VERT CRCKS&BULGING WALL.LINTEL@EXP2SAGGING.WOOD GIRDER SAGGING&CRCKD.ROOF JOIST POORLY SUPPRTD.BULKHEAD MASONRY WALL@EXP4 CRCKD.CONCRT ROOF SPALLING.OWNR TO RTAIN NYSPE-EVALU BLDG.LIC CNTRCTOR INSTLL TEMP SHORING.WRK UNDR SUPER VISION&DRCTION OF NYSPE.PE PROVIDE MEANS&METHODS.WRK STRT BY 8/29/21 |
| Jun 22, 2021 | V-DOB VIOLATION - ACTIVE | IMEGNCY-IMMEDIATE EMERGENCY ANYTHINGOPTIONAL | INSTALL A SIDEWALK SHED ALONG EXPOSURE 1 (25 STREET) APPROXIMATELY 105.0 LF AND ALONG EXPOSURE 2 (51ST AVENUE) APPROXIMATELY 300.0 LF |
| Apr 14, 2021 | V*-DOB VIOLATION - DISMISSED | AEUHAZ1-FAIL TO CERTIFY CLASS 1 NONE | FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION |
| Jan 27, 2020 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | AT THE TIME OF INSPECTION NOTED THAT A PARTIAL VACATE ORDER EXIXTS SIN CE 05/12/09 DUE TO COMPROMISED INTERIOR BRICK WALL AT REAR AND OBSERVE D VACTE AREA RE-OCCUPY UNAUTHORIZED WITH MULTIPLE FOOD CARTS AND A MOTOR VEHICLE PARKED ON THE VACATED AREA |
| Aug 25, 2017 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | FTM BLDG.STRL DEFECTS AT EASTERN PORT OF THE BLDG INCLUD:BLDG CRACKED& INSUFFICIENTLY TIED BRICK MASONRY EXT WALL.WARPED&OUT OF PLUMB BRICK MASONRY NORTH EXT WALL.ROOF FRAMING IS WARPED&SAGGING.REMEDY:REPAIR STRL DEFECTS IMMED.NYSPE EVAL ABOVE DEFECTS&BLDG.REPAIR UNDER DOB PERM REF DOB VIO 081617FEU40201AD FOR ADD'L JOB #421090688 REQUIREMENTS |
| Aug 16, 2017 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | PERM#421090688 CONSTRUCT DOC DO NOT ADDRESS EXIST STRL DEFECTS AT EASTERN PORT OF BLDG.BULGED,CRACKED&INSUFFICIENT TIED BRICK MASONRY EXT WALL.ROOF FRAMING IS WARPED&SAGGING.CRACKING NEAR TOP OF INTERIOR E/W BRICK WALL.REMEDY:REVISE PLANS&CONSTRUCT DOC TO CORRECT PRE EXIST STRL DEFECT LISTED.PROV CALC,STRL ANALYSIS&OTHER SUPPORT INFO |
| Aug 2, 2017 | V*-DOB VIOLATION - DISMISSED | IMEGNCY-IMMEDIATE EMERGENCY ANYTHINGOPTIONAL | IMEGNCY-IMMEDIATE EMERGENCY ANYTHINGOPTIONAL |
| Feb 24, 2017 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2015 INSPECTION REPORT |
| Feb 24, 2017 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2015 INSPECTION REPORT |
| Oct 1, 2015 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2014 INSPECTION REPORT |
| Oct 1, 2015 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2014 INSPECTION REPORT |
| Mar 3, 2015 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2013 INSPECTION REPORT |
| Mar 3, 2015 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2013 INSPECTION REPORT |
| May 15, 2014 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT |
| May 15, 2014 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT |
| Mar 1, 2013 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2011 INSPECTION REPORT |
| Mar 1, 2013 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2011 INSPECTION REPORT |
| Mar 26, 2012 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |
| Feb 8, 2012 | V*-DOB VIOLATION - DISMISSED | AEUHAZ1-FAIL TO CERTIFY CLASS 1 NONE | FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION |
| Jan 27, 2012 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |
| Dec 13, 2011 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2010 INSPECTION REPORT |
| Dec 13, 2011 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2010 INSPECTION REPORT |
| Jul 27, 2011 | V*-DOB VIOLATION - DISMISSED | AEUHAZ1-FAIL TO CERTIFY CLASS 1 NONE | FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION |
| Apr 6, 2011 | V*-DOB VIOLATION - DISMISSED | AEUHAZ1-FAIL TO CERTIFY CLASS 1 NONE | FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION |
| Mar 9, 2011 | V*-DOB VIOLATION - DISMISSED | AEUHAZ1-FAIL TO CERTIFY CLASS 1 NONE | FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION |
| Dec 31, 2009 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED |
| Jan 1, 2009 | V-DOB VIOLATION - ACTIVE | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |
| Jan 1, 2009 | V-DOB VIOLATION - ACTIVE | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |
| Jan 3, 2008 | V-DOB VIOLATION - ACTIVE | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |
| Oct 29, 2007 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |
| Aug 13, 2007 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |
| Jul 24, 2007 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |
| Jan 19, 2007 | V-DOB VIOLATION - ACTIVE | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |
| Jan 6, 2006 | V-DOB VIOLATION - ACTIVE | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |
| Jan 6, 2006 | V-DOB VIOLATION - ACTIVE | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |
| Jan 31, 2005 | V-DOB VIOLATION - ACTIVE | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |
| Jan 31, 2005 | V-DOB VIOLATION - ACTIVE | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |
| Feb 13, 2004 | V-DOB VIOLATION - ACTIVE | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |
| Feb 13, 2004 | V-DOB VIOLATION - ACTIVE | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |
| Mar 1, 1996 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |
| Mar 1, 1996 | VW-VIOLATION WORK WITHOUT PERMIT - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |