| Date | Status | Type | Summary |
|---|---|---|---|
| May 3, 2014 | V-DOB VIOLATION - ACTIVE | P-PLUMBING NONE | WORK WITHOUT A PERMIT; OBSERVED INI BASEMENT INSTALLED 2 BOILERS 1 HWH AS PER SUBMITTED OP128 BY RICHARD A BELLINI, LMP #1356 AT 2/2013. BUT IT IS NOT REPLACEMENT GAS LINES HAS BEEN ALTERED (NEW PIPING AFTER NEW FEE CONNECTION). REMEDY: OBTAIN A PERMIT OR RESTORE PREMISES TO PRIOR LEGAL CONDITION |
| May 3, 2014 | V-DOB VIOLATION - ACTIVE | P-PLUMBING NONE | WORK WITHOUT A PERMIT; OBSERVED IN BASEMENT INSTALLED 2 BOILERS, 1 HWH AS PER SUBMITTED OP-128 BY RICHARD A. BELLINI LMP#1356 AT 2/2013. BUT IT IS NOT REPLACMENT, GAS LINES HAS BEEN ALTERED, PIPE NOT PROPERLY SUPPORTED. REMEDY: OBTAIN PERMIT OR RESTORE PREMISES TO PRIOR LEGAL CONDITION |