Oct 28, 2021
CLOSED
7J
No Violation Warranted For Complaint At Time Of Inspection (I2)
- Complaint #
- 1585380
- DOB unit
- RTEU
- Inspected
- Oct 28, 2021
- Disposition date
- Oct 28, 2021
- Address on complaint
- 9 East 82 Street
- Community board
- Manhattan CB 8
-
Oct 28, 2021
CLOSED
7J
No Violation Warranted For Complaint At Time Of Inspection (I2)
- Complaint #
- 1585379
- DOB unit
- RTEU
- Inspected
- Oct 28, 2021
- Disposition date
- Oct 28, 2021
- Address on complaint
- 9 East 82 Street
- Community board
- Manhattan CB 8
-
Nov 5, 2020
CLOSED
Construction -Contrary/Beyond Approved Plans/Permits (83)
No Violation Warranted For Complaint At Time Of Inspection (I2)
- Complaint #
- 1557126
- DOB unit
- MAN.
- Inspected
- Nov 18, 2020
- Disposition date
- Nov 18, 2020
- Address on complaint
- 9 East 82 Street
- Community board
- Manhattan CB 8
-
Oct 21, 2020
CLOSED
Construction -Contrary/Beyond Approved Plans/Permits (83)
No Violation Warranted For Complaint At Time Of Inspection (I2)
- Complaint #
- 1556036
- DOB unit
- MAN.
- Inspected
- Oct 29, 2020
- Disposition date
- Oct 30, 2020
- Address on complaint
- 9 East 82 Street
- Community board
- Manhattan CB 8
-
Nov 19, 2018
CLOSED
Construction - Change Grade / Change Watercourse (06)
Inspector Unable To Gain Access - 2nd Attempt (C2)
- Complaint #
- 1495301
- DOB unit
- MAN.
- Inspected
- Mar 20, 2019
- Disposition date
- Mar 22, 2019
- Address on complaint
- 9 East 82 Street
- Community board
- Manhattan CB 8
-
Sep 2, 1992
CLOSED
Debris - Excessive (09)
No Violation Warranted For Complaint At Time Of Inspection (I2)
- Complaint #
- 1020931
- DOB unit
- MAN.
- Inspected
- Sep 9, 1992
- Disposition date
- Sep 15, 1992
- Address on complaint
- 9 East 82 Street
- Community board
- Manhattan CB 8
-
Mar 31, 1992
CLOSED
Debris - Excessive (09)
No Violation Warranted For Complaint At Time Of Inspection (I2)
- Complaint #
- 1018440
- DOB unit
- MAN.
- Inspected
- Jul 15, 1992
- Disposition date
- Jul 21, 1992
- Address on complaint
- 9 East 82 Street
- Community board
- Manhattan CB 8
-
Sep 20, 1991
CLOSED
Suspension Scaffold Hanging - No Work In Progress (70)
No Violation Warranted For Complaint At Time Of Inspection (I2)
- Complaint #
- 1015693
- DOB unit
- C & D
- Inspected
- Sep 30, 1991
- Disposition date
- Oct 10, 1991
- Address on complaint
- 9 East 82 Street
- Community board
- Manhattan CB 8