Manhattan Hell's Kitchen
DOB violations
Department of Buildings violations attached to this BIN or tax lot.
13 records
| Date | Status | Type | Summary |
|---|---|---|---|
| Jun 30, 2023 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION |
| Jun 20, 2023 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION |
| Jul 11, 2019 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | STRUCTURE RENDERED NON-COMPLIANCE DUE TO VEHICLE IMPACTED TO STORE FRONT OF THE RESTAURANT AND LEFT DOOR STUCK, DOES NOT OPEN. |
| Feb 20, 2017 | V*-DOB VIOLATION - Resolved | E-ELEVATOR ELEVATORREQUIRED | E-ELEVATOR ELEVATORREQUIRED |
| Jan 3, 2017 | V*-DOB VIOLATION - DISMISSED | ACC1-(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION ELEVATORREQUIRED | VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST |
| Nov 14, 2016 | V*-DOB VIOLATION - DISMISSED | ACC1-(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION ELEVATORREQUIRED | VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST |
| Mar 3, 2015 | V*-DOB VIOLATION - DISMISSED | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2013 INSPECTION REPORT |
| Jun 10, 2014 | V*-DOB VIOLATION - Resolved | E-ELEVATOR ELEVATORREQUIRED | E-ELEVATOR ELEVATORREQUIRED |
| Aug 7, 2013 | V*-DOB VIOLATION - Resolved | E-ELEVATOR ELEVATORREQUIRED | E-ELEVATOR ELEVATORREQUIRED |
| Jul 2, 2012 | V*-DOB VIOLATION - Resolved | E-ELEVATOR ELEVATORREQUIRED | E-ELEVATOR ELEVATORREQUIRED |
| Jul 9, 2009 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | INADEQUATE DETAILS ON APPROVED PLANS FOR 1. TOP OF CELLAR SLAB - 10'6" ON STRUC. DETAILS 3/31/09 1A. TO POF CELLAR SLAB IS 9' ON ARCH ELEVAT IONS. 2. DETAIL 5/56 HAS #4 REBAR @ 24" CC. DWELLING 1ST AND 2ND FLOO R SLAB INTO EXISTING BRICK WALLS WHERE 1' SEKMIC IS REQUIRED REMEDY: AMED PLANS TO INCLUDE CURRENT, CORRECTED REQUIREMENTS |
| Jun 1, 2009 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | MISCELLANEOUS VOILATIONS, FAILURE TO NOTIFY D.O.B. WITHIN 24-48 HOURS OF THE START OF EXCAVATION. NOTED: PARTIAL FOUNDATION COMPLETED APPROX. 60-70 FT AT EXP. 2 AND APPROX. 100 FT. AT EXP & NONOTIFICATION STOP ALL WORK - ENTIRE SITE - GIVEN TO D.O.B REMEDY: COMPLY WITH NOTICE OF VIOLATION. OFFICIALLY NOTIFY D.O.B. BY |
| Jan 16, 2008 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |