Manhattan Upper East Side-Lenox Hill-Roosevelt Island
DOB complaints
Department of Buildings complaints attached to this BIN. Category and disposition text come from DOB’s published code lists; some newer codes have no published description yet.
19 records
-
Nov 12, 2025
CLOSED
Boiler - Defective / Inoperative / No Permit (58)
Inspector Unable To Gain Access - 2nd Attempt (C2)
- Complaint #
- 1710063
- DOB unit
- BOILR
- Inspected
- Jan 2, 2026
- Disposition date
- Jan 2, 2026
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Jun 27, 2023
CLOSED
Building Shaking/Vibrating/Struct Stability Affected (30)
Inspector Unable To Gain Access - 2nd Attempt (C2)
- Complaint #
- 1641835
- DOB unit
- ERT
- Inspected
- Jun 29, 2023
- Disposition date
- Jun 29, 2023
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Jun 23, 2023
CLOSED
Building Shaking/Vibrating/Struct Stability Affected (30)
Ecb Violation Served (A8)
- Complaint #
- 1641502
- DOB unit
- ERT
- Inspected
- Jun 23, 2023
- Disposition date
- Jun 24, 2023
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Jun 9, 2023
CLOSED
Building Shaking/Vibrating/Struct Stability Affected (30)
No Violation Warranted For Complaint At Time Of Inspection (I2)
- Complaint #
- 1639121
- DOB unit
- ERT
- Inspected
- Jun 10, 2023
- Disposition date
- Jun 10, 2023
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Jun 7, 2023
CLOSED
Failure To Maintain (73)
Please See Complaint Number (H1)
- Complaint #
- 1638964
- DOB unit
- MAN.
- Inspected
- Aug 15, 2023
- Disposition date
- Aug 15, 2023
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Jan 4, 2021
CLOSED
7K
Inspector Unable To Gain Access - 2nd Attempt (C2)
- Complaint #
- 1561569
- DOB unit
- RTEU
- Inspected
- Jan 12, 2021
- Disposition date
- Jan 12, 2021
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
May 7, 2020
CLOSED
Boiler - Defective / Inoperative / No Permit (58)
Ecb Violation Served (A8)
- Complaint #
- 1542636
- DOB unit
- BOILR
- Inspected
- May 7, 2020
- Disposition date
- May 7, 2020
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Nov 9, 2019
CLOSED
Cse - Sweep (7G)
No Violation Warranted For Complaint At Time Of Inspection (I2)
- Complaint #
- 1527282
- DOB unit
- CSE
- Inspected
- Nov 9, 2019
- Disposition date
- Nov 9, 2019
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Aug 8, 2018
CLOSED
Construction -Contrary/Beyond Approved Plans/Permits (83)
Inspector Unable To Gain Access - 2nd Attempt (C2)
- Complaint #
- 1486477
- DOB unit
- MAN.
- Inspected
- Sep 5, 2018
- Disposition date
- Sep 7, 2018
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Jul 18, 2018
CLOSED
Construction -Contrary/Beyond Approved Plans/Permits (83)
No Violation Warranted For Complaint At Time Of Inspection (I2)
- Complaint #
- 1484529
- DOB unit
- MAN.
- Inspected
- Jul 27, 2018
- Disposition date
- Jul 28, 2018
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Jun 5, 2018
CLOSED
Construction -Contrary/Beyond Approved Plans/Permits (83)
Inspector Unable To Gain Access - 2nd Attempt (C2)
- Complaint #
- 1480850
- DOB unit
- MAN.
- Inspected
- Jun 21, 2018
- Disposition date
- Jun 23, 2018
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Dec 29, 2017
CLOSED
Work Contrary To Stop Work Order (86)
Complaint Unsubstantiated Based On Department Records (I1)
- Complaint #
- 1468941
- DOB unit
- ERT
- Inspected
- Dec 30, 2017
- Disposition date
- Dec 30, 2017
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Aug 29, 2017
CLOSED
Construction -Contrary/Beyond Approved Plans/Permits (83)
Ecb Violation Served (A8)
- Complaint #
- 1459089
- DOB unit
- MAN.
- Inspected
- Nov 2, 2017
- Disposition date
- Nov 3, 2017
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Aug 29, 2017
CLOSED
Building Shaking/Vibrating/Struct Stability Affected (30)
No Violation Warranted For Complaint At Time Of Inspection (I2)
- Complaint #
- 1459088
- DOB unit
- EXCAV
- Inspected
- Aug 30, 2017
- Disposition date
- Aug 30, 2017
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
May 31, 2017
CLOSED
Building Shaking/Vibrating/Struct Stability Affected (30)
No Violation Warranted For Complaint At Time Of Inspection (I2)
- Complaint #
- 1451935
- DOB unit
- ERT
- Inspected
- Jun 2, 2017
- Disposition date
- Jun 2, 2017
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Jan 7, 2017
CLOSED
Building Shaking/Vibrating/Struct Stability Affected (30)
Ecb Violation Served (A8)
- Complaint #
- 1440716
- DOB unit
- ERT
- Inspected
- Jan 8, 2017
- Disposition date
- Jan 9, 2017
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Nov 5, 2010
CLOSED
Illegal Hotel Rooms In Residential Buildings (4A)
Inspector Unable To Gain Access - 2nd Attempt (C2)
- Complaint #
- 1292386
- DOB unit
- SPOPS
- Inspected
- Jan 13, 2011
- Disposition date
- Jan 15, 2011
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Aug 2, 2010
CLOSED
Illegal Hotel Rooms In Residential Buildings (4A)
Inspector Unable To Gain Access - 2nd Attempt (C2)
- Complaint #
- 1286402
- DOB unit
- SPOPS
- Inspected
- Jan 13, 2011
- Disposition date
- Jan 15, 2011
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8
-
Aug 2, 2010
CLOSED
Illegal Hotel Rooms In Residential Buildings (4A)
Inspector Unable To Gain Access - 2nd Attempt (C2)
- Complaint #
- 1286391
- DOB unit
- SPOPS
- Inspected
- Jan 13, 2011
- Disposition date
- Jan 15, 2011
- Address on complaint
- 322 East 79 Street
- Community board
- Manhattan CB 8