| Feb 20, 2025 | V-DOB VIOLATION - ACTIVE | FISPHAZ-HAZARDOUS CONDITION (FACADE) FACADE REQUIRED | CYCLE 9B UNSAFE REPORT FILED |
| Dec 19, 2024 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | EMRGCY WRK ORDER: TO SECURE PUBLIC SAFETY - FISP3 FILED BY QEWI 12324 DUE TO IMMINENT HAZ CONDITIONS OBSERVED AT TIME OF INSPECTION OBSVRD CRACKED/SPALLED/LOOSE STUCCO MATERIALS, CRACKED CHIMNEY FLUE, WINDOW AC INSTALLED WITHOUT BRACKET AT EXP 1,2,3,4, (S,W,N,E ELEV). OWNER TO PROVDE IMMEDIATE/ADEQUATE SAFETY MEASURES TO ALL EXPO AS PER CODE |
| Feb 22, 2023 | V-DOB VIOLATION - ACTIVE | FISPNRF-NO REPORT AND / OR LATE FILING (FACADE) FACADE REQUIRED | FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 |
| Apr 29, 2021 | V*-DOB VIOLATION - DISMISSED | EGRADE-FAILURE TO POST ENERGY GRADE/SCORE NONE | FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3 |
| Nov 8, 2019 | V*-DOB VIOLATION - DISMISSED | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2017 INSPECTION REPORT |
| Jul 31, 2018 | V*-DOB VIOLATION - DISMISSED | FISPNRF-NO REPORT AND / OR LATE FILING (FACADE) FACADE REQUIRED | FAILED TO FILE FISP CYCLE 8B TECHNICAL REPORT BY 02/21/2018 |
| Jul 1, 2015 | V*-DOB VIOLATION - DISMISSED | AEUHAZ1-FAIL TO CERTIFY CLASS 1 NONE | FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION |
| Oct 22, 2013 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |
| Oct 22, 2013 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |
| Oct 22, 2013 | V*-DOB VIOLATION - DISMISSED | P-PLUMBING NONE | BORO COMMISSIONER HAS ISSUED A NOTICE TO IMMEDIATE STOP WORK ORDER DUE TO APPLICANTS WITHDRAWAL OF APPLICATION #121704361-01-PL REMEDY: STOP ALL WORK IMMEDIATELY -PLUMBING. SUBMIT ALL REQUIRED DOCUMENTS TO BORO COMMISSIONERS OFFICE FORTHWITH |
| Oct 22, 2013 | V*-DOB VIOLATION - DISMISSED | P-PLUMBING NONE | BORO COMMISSIONER HAS ISSUED A NOTICE OF STOP WORK ORDER DUE TO APPLICANTS WITHDRAWAL OF #121704343-01-PL REMEDY: STOP ALL WORK IMMEDIATLEY. SUBMIT ALL REQUIRED DOCUMENTS TO BORO COMMISSIONERS OFFICE FORTHWITH |
| Oct 21, 2013 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |
| Jul 26, 2005 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |
| Feb 27, 2001 | V*-DOB VIOLATION - DISMISSED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |