Nov 24, 2025
CLOSED
Electrical Wiring - Defective/Exposed, In Progress (59)
Inspector Unable To Gain Access - 2nd Attempt (C2)
- Complaint #
- 1711015
- DOB unit
- ELCTR
- Inspected
- Nov 25, 2025
- Disposition date
- Nov 27, 2025
- Address on complaint
- 168 East 89 Street
- Community board
- Manhattan CB 8
-
Nov 24, 2025
CLOSED
Construction Enforcement Work Order (Dob) (1X)
Compliance Inspection Performed (I3)
- Complaint #
- 1710982
- DOB unit
- MAN.
- Inspected
- Nov 25, 2025
- Disposition date
- Nov 25, 2025
- Address on complaint
- 168 East 89 Street
- Community board
- Manhattan CB 8
-
Nov 22, 2025
CLOSED
Electrical Wiring - Defective/Exposed, In Progress (59)
Inspector Unable To Gain Access - 2nd Attempt (C2)
- Complaint #
- 1710900
- DOB unit
- ELCTR
- Inspected
- Nov 24, 2025
- Disposition date
- Nov 24, 2025
- Address on complaint
- 168 East 89 Street
- Community board
- Manhattan CB 8
-
Nov 22, 2025
CLOSED
Building Under Structural Monitoring (2F)
N1
- Complaint #
- 1710899
- DOB unit
- ERT
- Inspected
- Nov 22, 2025
- Disposition date
- Nov 22, 2025
- Address on complaint
- 168 East 89 Street
- Community board
- Manhattan CB 8
-
Nov 22, 2025
CLOSED
Building Shaking/Vibrating/Struct Stability Affected (30)
Full Vacate Order Issued F (Y1)
- Complaint #
- 1710897
- DOB unit
- ERT
- Inspected
- Nov 22, 2025
- Disposition date
- Nov 22, 2025
- Address on complaint
- 168 East 89 Street
- Community board
- Manhattan CB 8
-
Jun 26, 1989
CLOSED
Residential Use - Illegal (48)
Inspector Unable To Gain Access - 2nd Attempt (C2)
- Complaint #
- 1002490
- DOB unit
- MAN.
- Inspected
- Aug 2, 1989
- Disposition date
- Aug 7, 1989
- Address on complaint
- 168 East 89 Street
- Community board
- Manhattan CB 8