Apr 6, 2018 V*-DOB VIOLATION - DISMISSED LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT
Apr 6, 2018 V*-DOB VIOLATION - DISMISSED LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT
Nov 4, 2015 V*-DOB VIOLATION - DISMISSED AEUHAZ1-FAIL TO CERTIFY CLASS 1 NONE FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
Jul 15, 2015 V*-DOB VIOLATION - DISMISSED AEUHAZ1-FAIL TO CERTIFY CLASS 1 NONE FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
Jul 15, 2015 V*-DOB VIOLATION - DISMISSED AEUHAZ1-FAIL TO CERTIFY CLASS 1 NONE FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
Jul 15, 2015 V*-DOB VIOLATION - DISMISSED AEUHAZ1-FAIL TO CERTIFY CLASS 1 NONE FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
Mar 14, 2015 VPW*-VIOLATION UNSERVED ECB-WORK WITHOUT PERMIT-DISMISSED P-PLUMBING NONE FULL STOP WORK ORDER - WORK WITHOUT A PERMIT; INSPECTION TIME AT 12:10 PM. AT TIME OF INSPECTION I OBSERVED ALL NEW GAS PIPES IN THE CELLAR & 1ST FLOOR SUPPLYING ALL COMMERICAL SPACE & BOILER IN THE CELLAR. ALSO NEW WATER LINES, VENTS, DRAIN LINES & FLOOR DRAINS WERE INSTALLED REMEDY: OBTAIN A PERMIT OR RESTORE TO PRIOR LEGAL CONDITION
Mar 1, 2013 V*-DOB VIOLATION - DISMISSED LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2011 INSPECTION REPORT
Dec 13, 2011 V*-DOB VIOLATION - DISMISSED LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2010 INSPECTION REPORT
Mar 26, 2002 V*-DOB VIOLATION - DISMISSED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED