Brooklyn East Flatbush-Erasmus
DOB violations
Department of Buildings violations attached to this BIN or tax lot.
7 records
| Date | Status | Type | Summary |
|---|---|---|---|
| Nov 22, 2023 | V*-DOB VIOLATION - DISMISSED | AEUHAZ1-FAIL TO CERTIFY CLASS 1 NONE | FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION |
| May 5, 2023 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | FTM.ON 5/5/23 A SCHOOL BUS IMPACTD THE EXP1,LOAD BEARNG WALL@THE 1STFL SALON&JUICE BAR COMMERCIAL SPACES.THE BRCK PIER@SALON WAS CLLPSD&PIER BTWN SALON&JUICE BAR DMGD.2NDFL JOISTS @APT2R SAGGNG TWRDS.OWNR TO RTAIN NYS PE TO EVAL ENT BLDG&FILE REPAIR DWGS W/DOB BLDG TO BE PRMANANTLY RPAIRD STARTNG BY 6/19/23&CMPLTD/SGND OFF BY 8/4/23 |
| May 5, 2023 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | EMERGENCY WORK ORDER.ON 5/5/23 BUS IMPACTD THE SALON.PIER@CENTER OF SALON@EXP1 CLLPSD&PIER BTWN SALON&JUICE BAR DMGD.LOAD BEARNGEXP1 WALL& 2-ROOF FLS INADEQUATELY SPPRTD&@RISK OF FRTHR CLLPSE.OWNR TO RTAIN NYSPE&GC TO IMMED INTALL TEMP WEATHERPROOFNG ALL WRK UNDR FULLTIME ONSITE NYS PE SPRVSN/DRCTN.FILE REPORT |
| May 5, 2023 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | EMERGENCY WORK ORDER.ON 5/5/23 BUS IMPACTED THE SALON.PIER@CENTER OF SALON @EXP1 CLLPSD&PIER BTWN SALON&JUICE BAR DMGD.LOAD BEARNG EXP1WALL &2ND-ROOF INADAQUATELY SPPORTD&@RISK OF FRTHR CLLPSE.BUS REMN.OWNR TO IMMED RTAIN GC TO INSTALL TGHTBOARD FENCE@CLLPSD ZONE ALONG CLARKSON AVE ENCLSNG 1PRKNG LANE.FILE FENCE W/IN 2 DAYS FROM START OF WORK |
| May 5, 2023 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | STRUCTURE RENDERED NON COMPLAINT DUE TO VEHICLE INTO BUILDING. THE BUILDING FACADE ,METAL AND GLASS STORE FRONT AND ROLL DOWN GATE DESTROYED. BRICK SECTION CRACKED AND DEFECTIVE. THE WOOD FLOOR IN APARTMENT 2R DISPLACED ABOUT 6 INCHES. INTERIOR WALLS ARE CRACKED VARIOUS LOCATIONS. |
| May 5, 2023 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | STRUCTURAL RENDERED NON COMPLAINT DUE TO VEHICLE IMPACT WHICH CAUSED STRUCTURAL DAMAGE TO THE STRUCTURE. A REPORT FROM A PE MUST BE FILED WITH DOB FOR STRUCTURAL STABILITY. |
| Mar 19, 2003 | V*-DOB VIOLATION - DISMISSED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |