6 records
| Date | Status | Type | Summary |
|---|---|---|---|
| May 15, 2025 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | FAILURE TO MAINTAIN.THE SOUTH FOUNDATION WALL DISPLACED SOUTH&THE SOUTH KLAN FROM 1ST TO ROOF IS LEANING TOWARDS THE EXCAVATION SITE@592 MARCY AVE.CRACK&PACKED FL NOTED@MANY LOCATIONS.OWNR TO ENGAGE NYSPE& LICENSED CNTRCTR TO RPAIR THE BLDG UNDER PERMIT COMPLETE&SIGN OFF REPAIRS BY 11/15/2025 |
| May 15, 2025 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | EMERGNECY WORK ORDER.THERE IS AN ACTIVE CONSTRUCTION SITE FOR A NEW BLDG(592 MARCY AVE)EXCAVATION IS COMPLETE@APPRX-14'BELOW GRADE.THE SOUTH WALL OF 590 MARCY AVE IS LEANING SOUTH&THE FDN WALL.IMMED INSTALL TEMP SHORNG ALNG SOUTH WALL FRM CELLAR TO ROOF UNDR DRCT& CNTINUOUS SPRVSN OF PE.SBMT MEANS&METHDS FOR REVIEW |
| May 15, 2025 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | STRUCTURE RENDERED NON-COMPLIANT. AT TIME OF INSPECTION OBSERVED WALL AT CELLAR LEVEL EXPOSURE#2 HAS BEEN COMPROMISED LEAVING PROPERTY UNSTABLE. ALSO OBSERVED CRACKS, WET FOUNDATION AND SPALLING CONCRETE AT EXP2 OF PROPERTY AT CELLAR LEVEL. ONGOING CONSTRUCTION AT ADJACENT PROPERTY 592 MARCY AVENUE. |
| May 15, 2025 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | STRUCTURE RENDERED NON COMPLIANT. AT TIME OF INSPECTION OBSERVED MAIN ENTRANCE DOOR AT MAIN ENTRANCE NOT LEVELED. ALSO OBSERVED CRACKED AND SPALLING CONCRETE AT EXP#1&3 OF PROPERTY FOUNDATION. AT APT 1,2,3 OBSERVED CRACKS AT WALLS, CRACKS NEAR WINDOW AND DAMAGED TILES AT MAIN ENTRANCE. ONGOING CONSTRUCTION AT ADJACENT PROPERTY 592 MARCY AVENUE. |
| May 15, 2025 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | REQUESTING AN ENGINEER REPORT DUE TO FOUNDATION OF PROPERTY BEING COMPROMISED. ONGOING CONSTRUCTION AT ADJACENT PROPERTY 592 MARCY AVENUE. AN ENGINEERING REPORT IS REQUIRED TO ASSESS AND RECTIFY THE STABILITY OF THE PROPERTY. |
| May 16, 2017 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | DAMAGED OBERVED TO HAVE BEEN SUSTAINED TO EXPOSURE # 1 DUE TO PARTIAL COLLAPSE AT 592 MARCY AVENUE |