| Date | Status | Type | Summary |
|---|---|---|---|
| Aug 29, 2025 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | FTC W/COMMISSIONER'S ORDER VIO#052025PI30103HZ & CONTROL#348271 DATED 05/20/25 REQUIRING OWNER TO PROV A CORRECTIVE ACTION PLAN BY 6/6/25 & START BLDG REPAIRS UNDER PERMIT BY 6/30/25 & COMPL/IGNED OF BY 8/8/25 AS OF TODAY 8/29/25 A CAP WAS NOT REC'D. IMMED COMPLY W COMMISSIONER'S ORDER TO PROVIDE A CORRECTIVE ACTION PLAN |
| Aug 29, 2025 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | FTC W/COMMISSIONER'S ORDER VIO#052125PI30101HZ,CONTROL#3488272 DATED 05/21/25 REQUIRING OWNER TO SUBMIT A CORRECTIVE ACTION PLAN BY 6/6/25 & START BLDG REPAIRS UNDER PERMIT&COMPL/SIGNED OFF BY 8/8/25 A CORRECTION ACTION PLAN WAS NOT REC'D. IMMED COMLY W/COMMISSIONER'S ORDER TO #052125PI30101HZ TO PROV A CORRECTION ACTION PLAN |
| May 22, 2025 | V*-DOB VIOLATION - DISMISSED | IMEGNCY-IMMEDIATE EMERGENCY ANYTHINGOPTIONAL | INSTALL ABOUT 25 LINEAR FEET OF SIDEWALK SHED ALONG FULL WIDTH OF EXPO SURE 1 |
| May 21, 2025 | V*-DOB VIOLATION - DISMISSED | IMEGNCY-IMMEDIATE EMERGENCY ANYTHINGOPTIONAL | INSTALL ABOUT 25 LINEAR FEET OF SIDEWALK SHED ALONG THE FULL WIDTH OF EXPOSURE 1 PLUS A 10 LINEAR FOOT EXTENSION BEYOND THE CORNER OF EXPOSU RE 1/4(TO INCLUDE THE AREA IN FRONT OF THE ENTRANCE TO THE ADJOINING 69 GRAND STREET BUILDING) |
| May 21, 2025 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | CORRECTIVE ACTION PLAN REQ'D. OBSVD DAMAGED BRICKS AT EXP1 AND STONE HEADERS IN DISREPAIR AT VARIOUS LOCATIONS. STEP CRACK AT EXP1 LEVELS UNDER WINDOW CLOSET TO EXP2 DETERIORATED OR MISSING MORTAR AT VARIOUS LOCATIONS. OWNER TO IMMED RETAIN A NYSPE TO EVAL ENTIRE BLDG & SUBMIT A CORRECTIVE ACTION PLAN TO PROACTIVEINSP@BUILDINGS.NYC.GOV |
| May 20, 2025 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | CORRECTIVE ACTION PLAN REQ'D. OBSVD @ EXP1 PARTIALLY BULGED OUTWARD ON 2-3-4 FLRS DECORATIVE STONE AROUND WINDOWS IN DISREPAIR,VERTICAL CRACKS @ EXP1/4 CORNER OF BLDG,BRICKS @ EXP4 WALL ARE BULGING ALONG ROOF LINE. OWNER TO IMMED RETAIN NYSPE TO EVAL THE ENTIRE BLDG & TO SUBMIT A CORRECTIVE ACTION PLAN TO PROACTIVEINSP@BUILDINGS.NYC.GOV |
| Jun 2, 2021 | V*-DOB VIOLATION - DISMISSED | BENCH-FAILURE TO BENCHMARK NONE | FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 |
| May 29, 2002 | VPW*-VIOLATION UNSERVED ECB-WORK WITHOUT PERMIT-DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | WORK WITHOUT A PERMIT; WORK NOTED TA 2ND FLOOR LEVEL PARTITION ERECTED TO CREATE 3 PIECE BATHROOM, BEDROOM KITCHEN WITH GAS STOVE AND SINK, ALSO NOTED FULL ELECTRICAL AND PLUMBING SEERVICES REMEDY: OBTAIN PERMIT OR RESTORE TO PRIOR LEGAL CONDITION |
| Aug 29, 2000 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | HAZARDOUS |