10 records
| Date | Status | Type | Summary |
|---|---|---|---|
| Mar 4, 2026 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | PER RETAINING WALL UNIT INSPECTED ON 07232025, RETAINED WALL AT REAR CONSTRUCTED CONTRARY TO ALT B01025469, SIGN-OFF 11062024. REVIEW APPLICATION REVEALED ON 10292024, OWNER'S PROCEED INSPECTED BY XIUCHENG LI, P.E., CERTIFIED FINAL INSPECTION DESPITE CONSTRUCTED NOT CONFORMED PLANS & HAVE SURRENDER THE RIGHT TO PERFORM INSPECTION |
| Aug 14, 2025 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | UNLAWFUL ACTS. FAILURE TO COMPLY WITH COMMISSIONER'S ORDER CONDITION: 072425CRW30702BH ISSUED ON JULY 24, 2025. UP TO TODAY'S DATE, NO PERMITS HAVE BEEN OBTAINED TO COMMENCE CONSTRUCTION FOR THE REBUILDING OF NEW RETAINING WALL. REMEDY:IMMEDIATELY COMPLY WITH COMMISSIONER'S ORDER 072425CRW30702BH ISSUED ON JULY 24, 2025 |
| Jul 24, 2025 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENT. NOTED: AT TIME OF INSPECION WE NOTED THAT THE RW CONSTRUCTION DOES NOT COMPLY WITH THE APPROVED CONSTRUCTION DOCUMENTS AS PER DOB JOB #B01025469 REMEDY: IMMEDIATELY DEMOLISH NON-COMPLIANT CONSTRUCTION. RECONSTRUCT AS PER APPROVED DRAWINGS. COMMENCE WORK NO LATER THAN AUGUST 7, 2025 |
| Jul 23, 2025 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | COMPROMISED STRUCTURE, NEEDS TO BE DEMOLISHED & REMOVED. AT TIME OF INSPECTION NOTED SUBJECT RETAINING WALL REPRESENT A SIGNIGICANT HAZARD TO PUBLIC SAFETY. UNSTABLE & AND FOUNDATION IS ABOVE GROUND AND POTENTIALLY DAMAGE THIS & ADJOINING PROPERTIES. REMEDY; IMMEDIATELY DEMOLISH RETAINING WALL AND COMPLY WITH NYC CODE |
| Oct 24, 2023 | V*-DOB VIOLATION - DISMISSED | EGNCY-EMERGENCY NONE | 1)ENCLOSED THE COLLAPSE ZONE WITH A CONSTRUCTION FENCE.2)IMMEDIATELY DEMOLISH ANY EXISTING REMNANTS OF THE REMAINING UNSTABLE RETAINING WALL STRUCTURE.3)ESTABLISH A STABLE 1:1 SLOPE STARTING FROM LOWEST ELEVATION (543 62 STREET) TO THE HIGH ELEVATION (550 61 STREET) |
| Oct 24, 2023 | V-DOB VIOLATION - ACTIVE | EGNCY-EMERGENCY NONE | ENCLOSED THE COLLAPSE ZONE WITH A CONSTRUCTION FENCE. 2) IMMEDIATELY D Y EXISTING REMNANTS OF THE REMAINING UNSTABLE RETAINING WALL STRUCTURE LISH A STABLE 1:1 SLOPE STARTING FROM LOWEST ELEVATION (543 62 STREET) GH ELEVATION (550 61 STREET) |
| Oct 23, 2023 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | WORK WITHOUT PERMIT; NOTED AT CELLAR LEVEL ERECTED FULL HEIGHT PARTITIONS FOR ROOMS AND BATH. INSTALLED WATER/ WASTE LINE FOR 3PC BATH(TOILET, SINK, TUB) AND RESIDENTIAL SINK. INSTALLED UNAUTHORIZED GAS LINE FOR GAS STOVE. |
| Oct 23, 2023 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | RESIDENCE CONVERTED FROM A LEGAL 2 FAMILY TO 3 FAMILY BY CREATING CLASS A APT AT CELLAR LEVEL. DOB RECORDS INDICATES RESIDENCE AS A 2 FAMILY AND NOW CONVERTED AND OCCUPIED AS A 3 FAMILY BY CREATING CLASS A APT AT CELLAR LEVEL WITH FULL KITCHEN, 3 PC BATHS AND SLEEPING QUARTER. |
| Sep 29, 2023 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | Y-3 STRUCTURE RENDERED NON COMPLAINT. AT TIME OF INSPECTION OBSERVED RETAINING WALL AT REAR OF THE BUILDING COLLAPSE ONTO REAR YARD. DUE TO HEAVY RAIN. VACATE ENTIRE REAR YARD. |
| Sep 29, 2023 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | AT TIME OF INSPECTION OBSERVED RETAINING WALL AT REAR OF THE BUILDING COLLAPSE ONTO REAR YARD. DUE TO HEAVY RAIN. ENGINEERS REPORT REQUESTED. |