| Date | Status | Type | Summary |
|---|---|---|---|
| Nov 5, 2008 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | FAILURE TO COMPLY WITH DOB STOP WORK ORDER #100208CEX02ADS AND PARTIAL RESCIND TO "INSTALL GUARDRAILS ONLY; BOTH DATED 10/02/08 NOTED: NB PE RMIT #310061697 SINCE SWO ISSUED, CONCRETED FOUNDATION AND STUD BEARIN G WALLS AT STAIRS HAVE BEEN INSTALLED FLOOR JOISTS RELOCATED REMEDY: STOP ALL WORK IMMEDUATELY AMEND PLANS FOR HEADER CHANGES AT EX |
| Oct 2, 2008 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | FAILURE TO SAFEGUARD ALL PERSONS AFFECTED BY CONSTRUCTION OPERATIONS NO GUARDRAILS OR SOLID ENCLOSURES OBSERVED AT 2ND FLOOR PERIMETER OR STAIR OPENINGS APPROX.10 FEET ABOVE GRADE. NB PERMIT# 310061697 REMEDY: SWO IMMEDIATELY. INSTALL FALL PROTECTION AND AMEND PLANS FOR FIRE DIVISION AT STAIR JOISTS. THEN CALL SEP/EX.FOR RE-INSPECTION |