6 records

Date Status Type Summary
Sep 21, 2021 V*-DOB VIOLATION - Resolved E-ELEVATOR ELEVATORREQUIRED E-ELEVATOR ELEVATORREQUIRED
Aug 19, 2020 V*-DOB VIOLATION - Resolved E-ELEVATOR ELEVATORREQUIRED E-ELEVATOR ELEVATORREQUIRED
Jan 5, 2017 V*-DOB VIOLATION - DISMISSED C-CONSTRUCTION OTHER OPTIONAL PRELIMINARY STRUCTURAL REVIEW REPORT, PREPARED BY GLEN LANGER, PE, CITED BOTH THE ORIGINAL STRUCTURAL DESIGN AND THE AS-BUILT STRUCTURE, ARE NOT CODE COMPLIANT FOR BOTH GRAVITY AND LATERAL SYSTEMS. THE RPRT CITES OVERALL CODE DEFICIENCIES; IT DOES NOT ADDRESS ALL CODE REQUIRED LATERAL LOADS AND IS DEEMED INCOMPLETE AND UNACCEPTED
Dec 16, 2016 V*-DOB VIOLATION - DISMISSED C-CONSTRUCTION OTHER OPTIONAL FAILURE TO COMPLY WTH COMMISSIONER'S ORDER #290749, REQUIRING OWNER TO START EMERGENCY WORK NO LATER THAN 12/5/16
Dec 2, 2016 V*-DOB VIOLATION - DISMISSED C-CONSTRUCTION OTHER OPTIONAL OWNER TO IMMEDIATELY INSTALL THE TEMPORARY BRACING SYSTEM TO LATERALLY SHORE THE BLDG. START WORK NO LATER THAN 12:00 PM 12/5/16. WORK TO BE PERFORMED UNDER PE SUPERVISION. FILE FOR PERMIT WITHIN 48 HOURS OF COMMENCING WORK. FAILURE TO COMPLY WILL RESULT IN CITY PERFORMING WORK
May 20, 2016 V*-DOB VIOLATION - DISMISSED C-CONSTRUCTION OTHER OPTIONAL FAILURE TO MAINTAIN: SLAB CRACKS IN GIRDERS FROM 1ST FL TO ROOF; STEEL FILLER BEAMS SIGNIFICANTLY DEFLECTED AT EACH FLOOR PROVIDE TEMP SHORING FROM ROOF TO-SLAB-ON-GRADE. RETAIN SURVEY COMPANY TO PERFORM SURVEY AND SUBMIT REPORTS ON COLUMN PLUMBING & SLAB SAGGIN G DEFLECTIONS. WORK TO START IMMEDIATELY