Brooklyn Bedford-Stuyvesant (West)
321 Willoughby Avenue, Brooklyn
DOB violations
Department of Buildings violations attached to this BIN or tax lot.
4 records
| Date | Status | Type | Summary |
|---|---|---|---|
| Jun 15, 2026 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | FAILURE TO COMPLY WITH COMMISSIONERS ORDER DATED 10/03/25. COMP # 3A3212166. ORDER DIRECTED COMMENCEMENT OF STABILIZATION BY 10/31/25. |
| Oct 3, 2025 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | UNPERM'D DEMO&ALT WRK,INTERIOR & EXP#3 WALLS REMOVED.ORIGINAL FRAMING REPLC'D BY CFS JOISTS. FLR HEIGHTS CHANGED.OPENING AT EXP #2 FDN WALL CELLAR ELEV. DROP'D. VERT + HORIZ EXT, BLDG. OPEN TO ELEMENTS. REMEDY: RETAIN NYS PE TO PERIODICALLY INSPECT SITE & PROVIDE INSPECTION RPORTS PROVIDE FIRST REPORT NO LATER THAN 10/10/25 |
| Oct 3, 2025 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | UNPERM'D DEMO&ALT WRK,INTERIOR & EXP#3 WALLS REMOVED.ORIGINAL FRAMING REPLC'D BY CFS JOISTS. FLR HEIGHTS CHANGED. OPENING@EXP #2 FDN WALL CELLAR ELEV. DROP'D. VERT + HORIZ EXT, BLDG. OPEN TO ELEMENTS. REMEDY: COMPLY W CODE. COMMENCE TEMPORARY STABILIZATION WORK UNDER PERMIT BY 10/31/25 |
| Sep 19, 2025 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | ATOI OBSERVED AT EXP 3 A 18'WX35'LX60'H HORIZONTAL EXTENSION. ALSO A TWO STORY VERTICAL EXTENSION. NO STRUCTURAL PLANS ON FILE. STRUCTURAL STABILITY IS IN QUESTION FOR EXISTING BLDG AND NEW FOUNDATION. ALSO FOR THE LIGHT GAUGE STEEL FRAMING AND C JOISTS THROUGHOUT. |