Nov 14, 2025 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION
Oct 29, 2025 V-DOB VIOLATION - ACTIVE C-CONSTRUCTION OTHER OPTIONAL FTC W/COMMISSIONER'S ORDER CONTROL#348190 VIO#090925PI30403TC DATED 9/9/25 REQUIRING OWNER TO PROVIDE A CORRECTIVE ACTION PLAN BY 10/9/25 &START BLDG REPAIRS UNDER PERMIT BY 11/9/25&COMPL/SIGNED OFF BY 12/8/25 AS OF 10/29/25 A CAP&EVIDENCE OF COMPL WORK WAS NOT REC'D IMMED COMPLY W/COMMISSIONER'S ORDER#348190 VIO#090925PI30403TC
Sep 9, 2025 V-DOB VIOLATION - ACTIVE C-CONSTRUCTION OTHER OPTIONAL CORRECTIVE ACTION PLAN REQ'D-OBSVD MISSING BRICKS AND SPALLING MASONRY THROUGHOUT EXP2. OWNER TO IMMED RETAIN REG DESIGN PROF TO EVAL THE ENTIRE BLDG AND TO SUBMIT A CORRECTIVE ACTION PLAN BY 10/9/25 ADRESSING ALL CONDITIONS W/PLAN,PHOTOS RECOMMENDING A TIME FRAME & REPAIRS T/BE COMPL. BLDG TO BE REPAIRED UNDER PERMIT START 11/9/25
Sep 23, 2024 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL LOW PRESSURE INSPECTION
Jun 30, 2023 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION
Jun 30, 2023 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION
Jun 20, 2023 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION
Apr 25, 2023 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION
Aug 29, 1995 V*-DOB VIOLATION - DISMISSED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED