Brooklyn South Williamsburg
DOB violations
Department of Buildings violations attached to this BIN or tax lot.
3 records
| Date | Status | Type | Summary |
|---|---|---|---|
| Jun 16, 2026 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | FTC-VIO#072125CEU30113PW(#3A22461)ORDERED 216 PENN ST LLC.TO HAVE EOR REVIEW NON-CONFORMANCE OF CONCRETE TESTING PROCEDURE & SUBMIT S/S ACCEPTANCE STATEMENT W/ ALT TESTING RESULTS BY9/12/25.AS OF 6/15/26, 216 PENN ST LLC.HAS NOT COMPLIED WITH COMMISSIONER'S ORDER.REMEDY: COMPLY W/ COMMISSIONER'S ORDER & CODE |
| Dec 24, 2025 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | AT TIME OF INSPECTION, OBSERVED UNPERMITTED WORK FOR VERTICAL AND HORIZONTAL EXTENSION. WORK HAS NOT BEEN PERMITTED TO PROCEED CAUSING SAFETY HAZARD TO STABILITY OF THE BUILDING. ENGINEERING REPORT TO BE SUBMITTED WITHIN 5 DAYS. |
| Jul 21, 2025 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | FAILURE TO PERFORM STANDARD-CURING SPECIMENS: DURING LAB INSPECTION @ HRF ON 7/1/2025, DOB OBSERVED DRY CYLINDERS STORED IMPROPERLY, NOT MEETING FINAL CURING REQUIREMENTS. REMEDY: COMPLY WITH CODES AND ASTM SUBMIT EOR-APPROVED ALTERNATE RESULTS BY 09/12/2025 |