| Date | Status | Type | Summary |
|---|---|---|---|
| Nov 14, 2025 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION |
| Nov 14, 2025 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION |
| Aug 28, 2025 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | REQUESTING AN ENGINEER REPORT DUE TO CHIMNEY AND EXTERIOR WALL(EXPOSURE 3) BEING IN A STATE OF DISREPAIR. AN ENGINEERING REPORT IS REQUIRED TO ASSESS AND RECTIFY THE DAMAGES PROPERTY HAS SUSTAINED. |
| Sep 23, 2024 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION |
| Sep 23, 2024 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION |
| Jun 30, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION |
| Jun 30, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION |
| Jun 30, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION |
| Jun 30, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION |
| Jun 20, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION |
| Jun 20, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION |
| Jun 20, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION |
| Jun 20, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION |
| Apr 25, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION |
| Apr 25, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION |
| Mar 16, 2020 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION |
| Mar 16, 2020 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION |
| Jun 22, 2018 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE 2016 ANNUAL HIGH PRESSURE BOILER INSPECTION |
| Jun 23, 2017 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE 2015 ANNUAL HIGH PRESSURE BOILER INSPECTION |
| May 15, 2014 | V*-DOB VIOLATION - DISMISSED | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE 2012 ANNUAL HIGH PRESSURE BOILER INSPECTION |
| Dec 3, 2011 | V-DOB VIOLATION - ACTIVE | C-CONSTRUCTION OTHER OPTIONAL | DOB VIOLATION ISSUED FOR MATTERS NOT PROVIDED. AUTOMIBLE STRUCK INTO THE BUILDING |
| Aug 9, 1994 | V-DOB VIOLATION - ACTIVE | ES-ELECTRIC SIGNS NONE | ES-ELECTRIC SIGNS NONE |