Brooklyn Bushwick (West)
DOB violations
Department of Buildings violations attached to this BIN or tax lot.
22 records
| Date | Status | Type | Summary |
|---|---|---|---|
| Nov 14, 2025 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION |
| Jun 30, 2023 | V*-DOB VIOLATION - DISMISSED | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION |
| Jun 30, 2023 | V*-DOB VIOLATION - DISMISSED | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION |
| Jun 30, 2023 | V*-DOB VIOLATION - DISMISSED | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION |
| Jun 30, 2023 | V*-DOB VIOLATION - DISMISSED | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION |
| Jun 20, 2023 | V*-DOB VIOLATION - DISMISSED | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION |
| Jun 20, 2023 | V*-DOB VIOLATION - DISMISSED | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION |
| Jun 20, 2023 | V*-DOB VIOLATION - DISMISSED | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION |
| Jun 20, 2023 | V*-DOB VIOLATION - DISMISSED | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION |
| Mar 16, 2020 | V*-DOB VIOLATION - DISMISSED | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION |
| Oct 15, 2019 | V*-DOB VIOLATION - Resolved | E-ELEVATOR ELEVATORREQUIRED | E-ELEVATOR ELEVATORREQUIRED |
| Sep 19, 2018 | V*-DOB VIOLATION - Resolved | E-ELEVATOR ELEVATORREQUIRED | E-ELEVATOR ELEVATORREQUIRED |
| Jun 22, 2018 | V*-DOB VIOLATION - DISMISSED | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE 2016 ANNUAL HIGH PRESSURE BOILER INSPECTION |
| Dec 16, 2016 | V*-DOB VIOLATION - DISMISSED | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE 2014 ANNUAL HIGH PRESSURE BOILER INSPECTION |
| Sep 9, 2016 | V*-DOB VIOLATION - Resolved | E-ELEVATOR ELEVATORREQUIRED | E-ELEVATOR ELEVATORREQUIRED |
| May 30, 2014 | V*-DOB VIOLATION - DISMISSED | ACC1-(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION ELEVATORREQUIRED | VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST |
| Dec 13, 2011 | V*-DOB VIOLATION - DISMISSED | EVCAT1-ELEVATOR ANNUAL INSPECTION / TEST ELEVATORREQUIRED | VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2010 INSPECTION/TEST |
| Oct 8, 2010 | V*-DOB VIOLATION - DISMISSED | VCAT1-ELEVATOR ANNUAL INSPECTION / TEST ELEVATORREQUIRED | VCAT1-ELEVATOR ANNUAL INSPECTION / TEST ELEVATORREQUIRED |
| May 21, 2010 | V*-DOB VIOLATION - Resolved | E-ELEVATOR ELEVATORREQUIRED | E-ELEVATOR ELEVATORREQUIRED |
| May 12, 2009 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | THE BORO COMMISSIONER REVOKED APPLICATION #310021883 ON 4-29-09 ALL WORK AS OF 05-12-09 HAS BEEN ORDERED STOPPED UNDER THIS APPLICATION REMEDY: STOP ALL WORK/MAKE SITE SAFE ONLY COMPLY WITH THE REVOKED APPL ICATION AND CONTACT THE BKLYN BORO OFFICE |
| Mar 7, 2006 | V*-DOB VIOLATION - Resolved | E-ELEVATOR ELEVATORREQUIRED | E-ELEVATOR ELEVATORREQUIRED |
| Jul 1, 2004 | V*-DOB VIOLATION - Resolved | E-ELEVATOR ELEVATORREQUIRED | E-ELEVATOR ELEVATORREQUIRED |