| Date | Status | Type | Summary |
|---|---|---|---|
| Jun 30, 2023 | V*-DOB VIOLATION - DISMISSED | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION |
| Jun 30, 2023 | V*-DOB VIOLATION - DISMISSED | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION |
| Jun 30, 2023 | V*-DOB VIOLATION - DISMISSED | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION |
| Apr 25, 2023 | V*-DOB VIOLATION - DISMISSED | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION |
| Oct 1, 2019 | V*-DOB VIOLATION - DISMISSED | RWNRF-RETAINING WALL NONE | FAILED TO FILE CYCLE 1 TECHNICAL REPORT BY 12/31/2018 PER RCNY 103-09 |
| Feb 13, 2004 | V*-DOB VIOLATION - DISMISSED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |
| Mar 19, 2003 | V*-DOB VIOLATION - DISMISSED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |
| Jun 4, 2001 | VW*-VIOLATION - WORK W/O PERMIT DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | WORK WITHOUT A PERMIT. NOTED: AIR-CONDITIONER UNIT INSTALLED AT ROOF AND THERE IS NO PERMIT FOR THE UNIT AT THE TIME OF RE-INSPECTION SECOND OFFENCE REMEDY: OBTAIN A PERMIT OR RESTORE TO PREVIOUS LEGAL CONDITION |
| May 8, 2000 | VW*-VIOLATION - WORK W/O PERMIT DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | WORK WITHOUT A PERMIT. WORK NOTED: AIR CONDITION UNIT INSTALLED AT ROO F NORTH SECTION |