Brooklyn Borough Park
DOB violations
Department of Buildings violations attached to this BIN or tax lot.
18 records
| Date | Status | Type | Summary |
|---|---|---|---|
| Jun 30, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION |
| Jun 30, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION |
| Jun 30, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION |
| Jun 30, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION |
| Jun 20, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION |
| Jun 20, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION |
| Jun 20, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION |
| Jun 20, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION |
| Apr 25, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION |
| Apr 25, 2023 | V-DOB VIOLATION - ACTIVE | HBLVIO-HIGH PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION |
| Sep 8, 2017 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | STOP ALL WORK IMMEDIATELY AND MAKE SITE SAFE CONTACT BOROUGH COMM. OFF ICE AT 718 802-3677 |
| Feb 24, 2017 | V-DOB VIOLATION - ACTIVE | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2015 INSPECTION REPORT |
| Oct 1, 2015 | V*-DOB VIOLATION - DISMISSED | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2014 INSPECTION REPORT |
| Mar 3, 2015 | V*-DOB VIOLATION - DISMISSED | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2013 INSPECTION REPORT |
| Dec 13, 2011 | V*-DOB VIOLATION - DISMISSED | LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED | VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2010 INSPECTION REPORT |
| May 2, 2008 | V*-DOB VIOLATION - DISMISSED | Z-ZONING NONE | Z-ZONING NONE |
| Jan 22, 2001 | V*-DOB VIOLATION - DISMISSED | C-CONSTRUCTION OTHER OPTIONAL | C-CONSTRUCTION OTHER OPTIONAL |
| Jul 25, 1994 | V*-DOB VIOLATION - DISMISSED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED | LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED |