19 records

Date Status Type Summary
May 1, 2024 V-DOB VIOLATION - ACTIVE IMEGNCY-IMMEDIATE EMERGENCY ANYTHINGOPTIONAL 1)AT EXP#1(FULTON STREET) ERECT APPROX 25LF OF SIDEWALK SHED 2)AT EXP #2(GRAND AVENUE) ERECT APPROX 60 LF OF SIDEWALK SHED 3)AT EXP #3 (PUTN AM AVENUE) ERECT APPROX 45LF OF SIDEWALK SHED FOR A TOTAL OF 130LF TO PROTECT THE PUBLIC
Jun 30, 2023 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION
Jun 30, 2023 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION
Jun 20, 2023 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION
Jun 20, 2023 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION
Feb 24, 2017 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2015 INSPECTION REPORT
Dec 13, 2011 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2010 INSPECTION REPORT
Dec 31, 2009 V-DOB VIOLATION - ACTIVE LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED
Feb 13, 2004 V-DOB VIOLATION - ACTIVE LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED
Mar 19, 2003 V-DOB VIOLATION - ACTIVE LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED
Mar 26, 2002 V-DOB VIOLATION - ACTIVE LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED
Jun 1, 2001 VW-VIOLATION WORK WITHOUT PERMIT - ACTIVE C-CONSTRUCTION OTHER OPTIONAL WORK WITHOUT A PERMIT. WORK NOTED: HANG CEILING CONSTRUCTED AT 1ST STY NORTH WEST STORE, ALSO WOOD PANEL WALLS AT PERIMETER, 2PC BATHROOM WITHOUT FRESH AIR VENTILATION AND PARTITION CONSTRUCTED REMEDY: OBTAIN A PERMIT IF FEASIBLE OR RESTORE TO PRIOR LEGAL CONDITION
Apr 20, 2000 VW-VIOLATION WORK WITHOUT PERMIT - ACTIVE C-CONSTRUCTION OTHER OPTIONAL WORK WITHOUT A PERMIT. WORK NOTED: HUNG CEILING CONSTRUCTED AT FIRST STORY NORTH WEST STORE. ALSO WOOD PANEL WALLS AT PERIMETER, TWO PIECE BATHROOM WITHOUT FRESH AIR VENTILATION AND PARTITIONS CONSTRUCTED REMEDY: OBTAIN A PERMIT IF FEASIBLE OR RESTORE THE PREMISES TO PRIOR LEGAL CONDITION
May 4, 1998 V-DOB VIOLATION - ACTIVE LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED
Sep 16, 1997 V-DOB VIOLATION - ACTIVE LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED
Aug 29, 1995 V-DOB VIOLATION - ACTIVE LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED
Jun 1, 1994 V-DOB VIOLATION - ACTIVE LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED
Aug 16, 1993 V-DOB VIOLATION - ACTIVE LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED
Jun 1, 1993 V-DOB VIOLATION - ACTIVE LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED LL6291-LOCAL LAW 62/91 - BOILERS BOILER REQUIRED